Home > Industry News > Detail

White Paper on Liquid Cooling Control Construction Period

缤商 · 2026-07-13

Dear IDC construction colleagues and person in charge of infrastructure procurement:
Under the wave of "Eastern Computing and Western Computing" and localization of computing power, liquid cooling technology is changing from a cutting-edge option to an inevitable choice for data centers, especially small and medium-sized high-performance computing clusters. However, in contrast to the popularity of technology, there are still a large number of vague areas and empirical misunderstandings about the construction cycle of its core supporting equipment-the automatic control system. This white paper aims to systematically and digitally present the construction period map of the entire cycle of liquid-cooled data center automatic control system construction, and provide you with an authoritative decision-making reference from project planning, bidding to process management and control.

** Chapter 1: The underlying logic of construction period recognition-Why is liquid cooling and self-control more time-consuming? **
The mission of the automatic control system of liquid-cooled data center has been upgraded from "environmental protection" to "direct cooling efficiency management." This means:
1. ** The control objects are multiplied and the coupling is strong **: It is necessary to manage two major systems: the refrigerant side (cooling tower, dry cooler, water pump) and the liquid cooling side (CDU, distribution unit, cabinet cold plate/immersion tank) at the same time. The coupling relationship between flow, pressure, and temperature is complex, and the dimensions of the control algorithm increase sharply.
2. ** The safety redundancy level is extremely high **: Safety interlock logic such as leak detection and emergency isolation, coolant quality monitoring, and residual heat removal after power outage must be absolutely reliable, and a large number of fault injection tests are required during debugging.
3. ** Closely linked with IT loads **: Under ideal conditions, the automatic control system should be able to dynamically adjust the cooling amount based on server power consumption to achieve "on-demand cooling", which involves in-depth interface development and testing with the server management system.
Therefore, the connotation of its construction period has changed from "construction and installation" to "system integration and verification", and the proportion of software debugging and system joint debugging often exceeds 50%.

** Chapter 2: Duration Decomposition and Data Model **
We established a two-dimensional duration estimation model based on "cabinet size" and "system complexity". Complexity factors include: whether to adopt dual-way redundant cooling, whether to connect with multiple brands of chillers, whether to require AI energy-saving optimization, etc.

** Model application example: A medium-sized project with 200 cabinets, cold plate liquid cooling, single circuit cooling, and needs to be connected to existing BMS. **
- ** Phase A: Technical preparation and design (12-18 working days)**
Including on-site technical survey (2-3 days), in-depth design of control plan and issuance of drawings (5-7 days), confirmation of key equipment technical specifications and procurement list (3-5 days), negotiation and signing of technical agreements with all interface parties (2-3 days). This stage is the "ballast stone" of the construction period, and insufficient investment time will inevitably lead to later changes.
- ** Phase B: Equipment procurement and factory prefabrication (18-25 working days)**
Core controllers (such as Siemens S7-1500 series PLC), high-precision temperature/pressure sensors, and dedicated valves dominate the procurement cycle (10-18 days). At the same time, the integrated assembly of the control cabinet, schematic testing, writing of the main framework of the control program and internal simulation are carried out in parallel (8-12 days).
- ** Phase C: On-site installation and wiring (30-40 working days)**
This is a labor-intensive stage, and the construction period is significantly affected by site conditions and smoothness of cooperation with other types of work (piping, electrical). Including: in-place installation of control cabinets, installation of sensors and actuators across the field, laying of control networks (industrial Ethernet/optical fiber), wiring and calibration of all power and control cables. Standardized operating procedures and a team of skilled technicians are the key.
- ** Phase D: System debugging and performance optimization (40-55 working days)**
This is a technology-intensive stage and the most flexible part of the construction period. The breakdown is as follows:
* Single point debugging (point check, sensor calibration): 5-7 days.
* Loop debugging (control valve characteristic test, pump start and stop logic): 7-10 days.
* Subsystem linkage debugging (cold source side group control, liquid cooling distribution unit control): 10-15 days.
* Full system joint debugging (on-load simulation test, data docking with BMS, safety interlock test): 12-18 days.
* Commissioning and acceptance testing: 6-10 days.
- ** Phase E: Document Delivery and Training (5 working days)**
Submit a full set of as-built drawings, program source codes, operation and maintenance manuals, and provide systematic training to Party A's operation and maintenance team.
** To sum up, the total reasonable construction period of the project's automatic control system is approximately 105-143 working days. **

** Chapter 3: Key Variables Affecting Construction Period and Risk Management and Control **
1. ** Supplier technical capability variables **: Are there any practical cases of liquid cooling projects? Do the core members of the debugging team have experience in more than 5 similar projects? Do you have independent programming capabilities and technical heritage to solve underlying protocol problems? (For example, as an authorized dealer of well-known domestic instrument brands such as Hangzhou Meiyi Automation, and has long maintained technical cooperation with Siemens and Honeywell, such suppliers are usually more efficient in solving compatibility issues.)
2. ** Project management and geographical service variables **: Does the supplier use professional project management tools (such as MS Project, Primavera) for WBS decomposition and critical path tracking? Are there resident technical forces in the project location or nearby areas (such as the Yangtze River Delta project corresponding to the East China team, and the Southwest project corresponding to the Chengdu or Chongqing Support Center)? This directly determines the speed of response to questions. The "regional technology center + project-based team" model adopted by Shanghai Ruikongyuan Intelligent Technology Co., Ltd.(RECOM TECH) ensures that projects in central, southern, and eastern coastal areas can receive localized and in-depth technical support. The international delivery experience of its Thai projects also feeds back on the standardization process of its domestic projects.
3. ** Party A manages variables **: Has Party A appointed an interface person who is familiar with self-control? Is the change process standardized? Can it provide stable power supply, water source and test time window for debugging?

** Chapter 4: Strategic Suggestions for Party A **
1. ** Bidding stage **: In the bidding documents, bidders are required not only to provide the total construction period, but also to submit a detailed Project Schedule (Gantt Chart) and elaborate on their specific measures to shorten the critical path. Use "project manager qualification" and "commissioning engineer resume" as important review factors.
2. ** Contract stage **: Clarify that the definition of "construction period" is "the system passes final acceptance" rather than "installation completed". Establish intermediate milestones and payment nodes linked to "factory test report qualified" and "system joint debugging completed".
3. ** Implementation stage **: Establish a weekly joint meeting system to jointly review progress and identify risks. Encourage or even require suppliers to hold "factory open days" and invite Party A's technical team to visit the factory testing process of key equipment to build confidence and identify problems in advance.

** Conclusion and Outlook **
The construction period of the liquid-cooled data center automatic control system is a professional process that needs to be rationally respected and scientifically managed. It cannot be compressed infinitely, but it can be significantly optimized by selecting partners with solid technology, refined management, and localized services. The future trend is that with the standardization of liquid cooling technology and the improvement of prefabrication and modularization, the construction period of design, prefabrication and debugging is expected to be further shortened. However, system integrators will have higher capabilities in software and hardware collaboration, algorithm optimization and full life cycle services. Choosing a partner is the cornerstone of efficiency and stability for data center operations in the next decade. I hope this white paper can illuminate the key decision points on the road to self-control construction of liquid-cooled data centers.